Rural development is the part of the Indian economy syllabus where a handful of numbers decide the marks: how many days of work are guaranteed, in how many days the work or the allowance must come, how far from home the work may be, and what share of the cost the Centre bears. The Ministry of Rural Development runs the programmes, and the Mahatma Gandhi National Rural Employment Guarantee Act is the only one of them that gives a legal right rather than a benefit.
MGNREGA: the legal guarantee
The National Rural Employment Guarantee Act was passed by Parliament in 2005 and came into force on 2 February 2006 in 200 of the poorest districts, the first launch being at Bandlapalli in the Anantapur district of Andhra Pradesh. It was extended to 130 more districts in 2007-08, to all rural districts from 1 April 2008, and renamed the Mahatma Gandhi National Rural Employment Guarantee Act on 2 October 2009. It remains the largest employment guarantee programme in the world.
| Provision | What the Act says |
|---|---|
| Guarantee | At least 100 days of unskilled manual wage employment in a financial year to every rural household whose adult members volunteer for it |
| Nature of the scheme | Demand driven: work follows an application, so the budget follows the demand and is not a fixed target |
| Job card | Issued to a registered household, carrying the names and photographs of the adult members |
| Deadline for work | Employment within 15 days of the application, failing which the State pays an unemployment allowance |
| Deadline for wages | Wages to be paid within 15 days of the closure of the muster roll, with compensation for delay |
| Distance | Work within 5 kilometres of the village; beyond that, an extra 10 per cent of the wage rate is paid |
| Women | Priority such that at least one third of the beneficiaries are women; equal wages for women and men |
| Worksite facilities | Drinking water, shade, first aid and a creche where there are five or more children below six years |
| Wage and material | The cost of wages to material in the works taken up must be at least 60:40, and contractors and labour displacing machinery are banned |
| Social audit | Section 17: the Gram Sabha monitors the works and conducts the social audit; the Gram Panchayat executes at least half the works by cost |
The money is shared by rule. The Centre bears the whole of the unskilled wage cost and 75 per cent of the material cost including the wages of skilled and semi-skilled workers, while the State bears the remaining 25 per cent of the material cost and the whole of the unemployment allowance. Administrative expenses are capped at a small share of the outlay. Wage rates are notified by the Central Government under Section 6 of the Act and revised, so the number itself changes from year to year and from State to State; what the examiner tests is the rule, not the rate.
The machinery and the works
- The District Programme Coordinator, usually the District Collector or the chief executive of the Zila Parishad, and the Programme Officer at the block level run the scheme; an Ombudsperson in each district hears grievances.
- The Central Employment Guarantee Council and the State Councils advise on and monitor the Act.
- Schedule I lists the permissible works in four categories: natural resource management such as water conservation and afforestation; individual assets for the poorest households such as wells, cattle sheds and farm ponds; common infrastructure for self help groups under the livelihoods mission; and rural infrastructure such as roads, drains and playfields.
- Payment is made into bank or post office accounts by direct benefit transfer, and attendance is captured through a mobile monitoring application, which is why questions on transparency measures mention Aadhaar-based payment, geo-tagging of assets and the public muster roll.
The other rural development programmes
| Programme | Year | Purpose |
|---|---|---|
| Pradhan Mantri Gram Sadak Yojana | 25 December 2000 | All weather roads to unconnected habitations, generally those above 500 persons in the plains and 250 in hill, tribal and desert areas |
| Pradhan Mantri Awas Yojana Gramin | 2016 | A pucca house with basic amenities for the rural homeless and those in kutcha houses, with higher assistance in hill, north-eastern and difficult areas, plus 90 days of MGNREGA wage support |
| Deendayal Antyodaya Yojana - National Rural Livelihoods Mission | 2011 | Self help groups of rural women, with revolving fund, community investment fund and interest subvention; restructured from the Swarnajayanti Gram Swarozgar Yojana |
| Deen Dayal Upadhyaya Grameen Kaushalya Yojana | 2014 | Placement linked skill training for rural youth |
| Sansad Adarsh Gram Yojana | 11 October 2014 | Members of Parliament adopt and develop model villages; the date is Jayaprakash Narayan's birth anniversary |
| Shyama Prasad Mukherji Rurban Mission | 2016 | Urban amenities in clusters of villages, the idea of rurban growth centres |
| National Social Assistance Programme | 1995 | Old age, widow and disability pensions and the family benefit scheme for the rural poor |
What came before MGNREGA
Rural employment programmes have a long line of ancestors, and questions on firsts often come from it. The Community Development Programme of 1952 was the first integrated effort, followed by the National Extension Service of 1953; the Balwant Rai Mehta Committee of 1957 recommended democratic decentralisation and led to panchayati raj. Then came the Integrated Rural Development Programme at the end of the 1970s, the National Rural Employment Programme of 1980, the Rural Landless Employment Guarantee Programme of 1983, the Jawahar Rozgar Yojana of 1989 which merged the last two, the Employment Assurance Scheme of 1993, the Sampoorna Grameen Rozgar Yojana of 2001 and the National Food for Work Programme of 2004, whose districts became the first MGNREGA districts. The 73rd Constitutional Amendment of 1992, which added Part IX and the Eleventh Schedule with its 29 subjects, gave the panchayats the constitutional standing that lets them execute these works today.
Exam Point of View
Almost every question is a number or a pairing. The numbers are 100 days of work, 15 days for providing work and 15 days for paying wages, 5 kilometres of distance with 10 per cent extra beyond it, one third women, 60:40 wages to material, and the Centre's share of 100 per cent of unskilled wages and 75 per cent of material cost. The dates are 2 February 2006 for coming into force, 1 April 2008 for full coverage and 2 October 2009 for the renaming, with Anantapur in Andhra Pradesh as the first district. The pairings are Section 17 with the Gram Sabha and social audit, the Ministry of Rural Development as the implementing ministry, and scheme to purpose: PMGSY for roads, PMAY-Gramin for houses, DAY-NRLM for self help groups, DDU-GKY for skills and SAGY for model villages. A frequent trap is to call MGNREGA a supply driven scheme; it is demand driven, and a second trap is to make the Centre pay the unemployment allowance, which is the State's liability.
Important Facts
| Guarantee | 100 days of unskilled manual work per rural household in a financial year |
|---|---|
| Act passed and in force | Passed 2005; in force 2 February 2006 in 200 districts |
| First launch | Bandlapalli, Anantapur district, Andhra Pradesh |
| Full coverage | All rural districts from 1 April 2008 |
| Renamed | Mahatma Gandhi NREGA on 2 October 2009 |
| Unemployment allowance | If work is not given within 15 days; paid by the State Government |
| Payment of wages | Within 15 days of the closure of the muster roll |
| Distance of worksite | Within 5 km, else 10 per cent extra wage |
| Share of women | At least one third of beneficiaries |
| Wage to material ratio | At least 60:40 |
| Social audit | Gram Sabha, under Section 17 of the Act |
| Cost sharing | Centre 100 per cent of unskilled wages and 75 per cent of material cost |
| Implementing ministry | Ministry of Rural Development |
| PMGSY | Launched 25 December 2000 for all weather rural roads |
| First rural development programme | Community Development Programme, 1952 |
Practice MCQs on this topic
Enacted on 7 September 2005, the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) in India entitles, by demand, every rural household to a minimum of _______ of paid work each year at minimum wage.
- A.120 days
- B.150 days
- C.180 days
- D.100 days
Show answer
Section 3 of the Act obliges the State Government to provide at least one hundred days of unskilled manual wage employment in a financial year to every rural household whose adult members volunteer for such work, and the guarantee belongs to the household, not to each member.
Read the full explanation →The National Rural Employment Guarantee Act came into force on which date?
- A.2 October 2005
- B.2 February 2006
- C.1 April 2008
- D.2 October 2009
Show answer
The correct answer is B, 2 February 2006, when the Act came into force in 200 of the poorest districts of the country, the first launch taking place at Bandlapalli in the Anantapur district of Andhra Pradesh.
Read the full explanation →On which date was the National Rural Employment Guarantee Act renamed after Mahatma Gandhi?
- A.2 February 2006
- B.15 August 2008
- C.2 October 2009
- D.2 October 2014
Show answer
The Act was renamed on Gandhi Jayanti in 2009, and from then it has been known as MGNREGA, the Mahatma Gandhi National Rural Employment Guarantee Act.
Read the full explanation →Under MGNREGA, an unemployment allowance becomes payable if work is not provided within
- A.7 days of the application
- B.15 days of the application
- C.30 days of the application
- D.45 days of the application
Show answer
If employment is not provided within fifteen days of the application, or of the date from which work is sought, whichever is later, the applicant becomes entitled to an unemployment allowance, which the State Government pays from its own funds.
Read the full explanation →Under MGNREGA, work has to be provided within what distance of the applicant's village?
- A.2 kilometres
- B.5 kilometres
- C.10 kilometres
- D.There is no limit on distance
Show answer
The Act requires that work be provided ordinarily within five kilometres of the village of the applicant, and if the worksite is farther away, the worker is paid an extra ten per cent of the wage rate to meet the cost of travel and living.
Read the full explanation →What is the minimum share of women among MGNREGA beneficiaries required by the Act?
- A.One fourth
- B.One third
- C.One half
- D.Two thirds
Show answer
Priority has to be given to women in such a way that at least one third of the beneficiaries are women who have registered and asked for work, and the Act also requires equal wages for women and men for the same work.
Read the full explanation →Under which section of MGNREGA does the Gram Sabha conduct the social audit of works?
- A.Section 3
- B.Section 6
- C.Section 17
- D.Section 27
Show answer
The correct answer is C, Section 17, which makes the Gram Sabha responsible for monitoring the execution of works within the panchayat and for conducting a regular social audit of all the projects taken up under the scheme, with every record open to public inspection.
Read the full explanation →What wage to material ratio has to be maintained in works taken up under MGNREGA?
- A.40:60
- B.50:50
- C.60:40
- D.75:25
Show answer
At least sixty per cent of the cost of the works must go on wages and not more than forty per cent on material, so that the scheme remains an employment programme rather than a construction programme.
Read the full explanation →The Pradhan Mantri Gram Sadak Yojana, meant for all weather rural roads, was launched in which year?
- A.1996
- B.2000
- C.2005
- D.2014
Show answer
The Pradhan Mantri Gram Sadak Yojana was launched on 25 December 2000 to connect unconnected habitations with all weather roads, generally those with a population above five hundred in the plains and above two hundred and fifty in hill, tribal and desert areas, and it later added the upgradation of…
Read the full explanation →Which rural development mission organises rural women into self help groups for livelihood support?
- A.DAY-NRLM, also called Aajeevika
- B.PMAY-Gramin
- C.DDU-GKY
- D.SPMRM
Show answer
It organises poor rural women into self help groups, federates them at the village and block level, and supports them with a revolving fund, a community investment fund and interest subvention on bank loans.
Read the full explanation →Which was the first integrated programme of rural development in independent India?
- A.The Integrated Rural Development Programme
- B.The Community Development Programme
- C.The Jawahar Rozgar Yojana
- D.The Employment Assurance Scheme
Show answer
Its weaknesses led to the Balwant Rai Mehta Committee of 1957, whose recommendation of democratic decentralisation gave India panchayati raj.
Read the full explanation →Frequently Asked Questions
How many days of work does MGNREGA guarantee?
At least 100 days of unskilled manual wage employment in a financial year to every rural household whose adult members volunteer for such work. The guarantee belongs to the household and not to each individual, and additional days can be allowed by the Centre in drought or disaster affected areas.
What happens if work is not provided within 15 days?
The applicant becomes entitled to an unemployment allowance, which is paid by the State Government out of its own funds, at a rate fixed under the Act. This liability is the reason the scheme is called a legal guarantee rather than a welfare scheme.
Who conducts the social audit of MGNREGA works?
The Gram Sabha, under Section 17 of the Act, which monitors the execution of works within the panchayat and conducts a regular social audit of all projects, with the records open to any citizen. Independent social audit units in the States now support the process.
How is the cost of MGNREGA shared between the Centre and the States?
The Central Government bears the whole of the wage cost of unskilled manual work and 75 per cent of the material cost, including the wages of skilled and semi-skilled workers. The State Government bears the remaining 25 per cent of the material cost and the entire unemployment allowance.
Which scheme builds all weather roads in villages?
The Pradhan Mantri Gram Sadak Yojana, launched on 25 December 2000, which connects unconnected habitations, generally those with a population above 500 in the plains and above 250 in hill, tribal and desert areas, and now also upgrades the existing rural road network.
Why is MGNREGA called demand driven?
Because work is provided on application by the household rather than according to a target fixed in advance, and the budget has to follow the number of people who ask for work. A scheme with a fixed allocation and a fixed number of beneficiaries, like most welfare schemes, is supply driven by contrast.
Sources
- The Mahatma Gandhi National Rural Employment Guarantee Act, 2005, with Schedules I and II — Ministry of Rural Development
- Indian Economic Development (Class XI), chapters on rural development and employment — NCERT
- Programme guidelines of PMGSY, PMAY-Gramin and DAY-NRLM — Ministry of Rural Development