Static GK decides the General Awareness score in SSC MTS. The 2025 notice keeps the syllabus at the 10th Standard: History, Geography, Art and Culture, Civics and Economics under Social Studies, General Science and Environmental Studies. Most of the 25 questions in Session-II come from these areas. History asks the Harappan sites, the Mauryas and Guptas, the Sultanate and Mughal rulers and the freedom movement. Geography asks rivers, soils, crops, minerals, national parks, States, capitals and neighbours. Civics asks the Constitution's Parts, Schedules and Articles, Fundamental Rights and Duties, the President, Parliament, the Supreme Court and local government. Economics asks basic terms, the RBI, taxes and schemes. General Science covers Class 6 to 10 Physics, Chemistry and Biology, and Environmental Studies asks ecosystems, pollution and conservation. This page holds GK24's topic-wise GK notes for SSC MTS, written as short facts and tables at exactly that level so a topic can be finished in one sitting and revised in ten minutes. Read a topic, then solve its previous-year questions and quiz on this site to see what stayed with you, and keep the notes for the last-week revision before the CBE.

SSC MTS GK Questions with Answers

Q4821.Important Days & DatesMedium

National Space Day is observed in India on 23 August to mark which achievement?

  1. A.The launch of Aryabhata
  2. B.The Mars Orbiter Mission entering orbit
  3. C.The soft landing of Chandrayaan 3 near the lunar south pole
  4. D.The first flight of the PSLV
Show answer
Correct answer: C. The soft landing of Chandrayaan 3 near the lunar south pole

The Vikram lander of Chandrayaan 3 touched down near the south pole of the Moon on 23 August 2023, making India the first country to land in that region, and the date was declared National Space Day in memory of the achievement.

Q4823.Important Days & DatesMedium

Which of the following days is observed on 9 August?

  1. A.Hiroshima Day
  2. B.Quit India Movement Day
  3. C.National Handloom Day
  4. D.Partition Horrors Remembrance Day
Show answer
Correct answer: B. Quit India Movement Day

The ninth of August is observed as Quit India Movement Day, or August Kranti Diwas, because the movement launched at the Bombay session of the Congress led to mass action from that date in 1942.

Q4824.Important Days & DatesMedium

International Tiger Day is observed every year on

  1. A.28 July
  2. B.29 July
  3. C.3 March
  4. D.12 August
Show answer
Correct answer: B. 29 July

International Tiger Day, also called Global Tiger Day, is observed on 29 July every year to draw attention to the conservation of the tiger and of its habitat, and it is a date on which tiger range countries report on their efforts.

Q4830.Computer AwarenessHard

The technique of placing output in a queue on the disk so that a slow device such as a printer does not hold up the processor is called

  1. A.Paging
  2. B.Spooling
  3. C.Caching
  4. D.Swapping
Show answer
Correct answer: B. Spooling

Spooling stands for simultaneous peripheral operations on line. The operating system writes the data meant for a slow device into a queue on the disk and lets the processor go on with other work, while the device picks jobs out of that queue at its own pace.

Q4832.Computer AwarenessHard

An operating system that guarantees a response within a strictly fixed time limit, as needed in missile control and medical equipment, is called

  1. A.Batch operating system
  2. B.Real time operating system
  3. C.Time sharing operating system
  4. D.Distributed operating system
Show answer
Correct answer: B. Real time operating system

A real time system is judged not only by whether it gives the right answer but by whether it gives that answer inside a fixed deadline.

Q4838.Computer AwarenessMedium

Which scheduling algorithm allots a fixed time slice to every process in rotation and is therefore used in time sharing systems?

  1. A.First Come First Served
  2. B.Shortest Job First
  3. C.Round Robin
  4. D.Priority scheduling
Show answer
Correct answer: C. Round Robin

In Round Robin scheduling every ready process is given the processor for a fixed period called the time quantum, and when that period expires the process is moved to the back of the queue and the next one is served.