Skip to content
GK24
Environment & EcologyHard

Which category of projects under the EIA Notification of 2006 does NOT require screening?

  1. A.Category A
  2. B.Category B1
  3. C.Category B2
  4. D.All categories require screening

Correct answer

A. Category A

Explanation

The correct answer is A, Category A. For a Category A project, prior environmental clearance from the central government is compulsory by the very fact of its listing in the schedule, so there is nothing for a screening stage to decide and the process begins at scoping. Options B and C are wrong because screening is precisely the stage that sorts Category B projects into B1, which must prepare a full EIA report, and B2, which need not; a B1 or B2 label is the outcome of screening and cannot exist without it. Option D is wrong because it contradicts the structure of the notification, which expressly exempts Category A projects from screening. Remembering that screening belongs only to Category B is enough to answer several variants of this question.

Read the full article: Environmental Impact Assessment: Process and Categories

View all
Q1.Environment & EcologyMedium

Which country was the first to make Environmental Impact Assessment a statutory requirement?

  1. A.United Kingdom
  2. B.United States of America
  3. C.Sweden
  4. D.India
Show answer
Correct answer: B. United States of America

Explanation

The correct answer is B, the United States of America. The National Environmental Policy Act of 1969, which came into force in 1970, required every agency of the American federal government to prepare a statement of the environmental effects of any major action it proposed, and that requirement is taken as the beginning of environmental impact assessment as a legal duty anywhere in the world. Option A is wrong because the United Kingdom adopted assessment later, under the directives of the European Community. Option C is wrong because Sweden hosted the United Nations Conference on the Human Environment at Stockholm in 1972, which is a different landmark and a common point of confusion. Option D is wrong because India began appraising river valley projects administratively only in 1978 and made assessment a legal requirement by notification in 1994.

Q2.Environment & EcologyEasy

The Environmental Impact Assessment Notification in India is issued under which Act?

  1. A.Wild Life (Protection) Act, 1972
  2. B.Water (Prevention and Control of Pollution) Act, 1974
  3. C.Environment (Protection) Act, 1986
  4. D.Forest (Conservation) Act, 1980
Show answer
Correct answer: C. Environment (Protection) Act, 1986

Explanation

The correct answer is C, the Environment (Protection) Act, 1986. Section 3 of that Act gives the central government power to take all measures it thinks necessary to protect and improve the quality of the environment, and the EIA Notifications of 1994 and 2006 were both issued under it. The Act was passed in the aftermath of the Bhopal gas tragedy of 1984 and is an umbrella law for environmental regulation. Option A is wrong because the Wild Life (Protection) Act of 1972 deals with protected areas, schedules of species and hunting. Option B is wrong because the Water Act of 1974 created the pollution control boards and deals with effluent standards and consent to operate. Option D is wrong because the Forest (Conservation) Act of 1980 governs the diversion of forest land, for which a separate forest clearance is needed.

Q3.Environment & EcologyEasy

The Environmental Impact Assessment Notification currently in force in India was issued in which year?

  1. A.1986
  2. B.1994
  3. C.2006
  4. D.2010
Show answer
Correct answer: C. 2006

Explanation

The correct answer is C, 2006. The EIA Notification of 2006 replaced the earlier notification of 1994 and reorganised the whole clearance process, chiefly by dividing projects into Category A, appraised and cleared at the central level, and Category B, appraised and cleared at the state level, and by laying down the four stages of screening, scoping, public consultation and appraisal. Option A is wrong because 1986 is the year of the parent Act, the Environment (Protection) Act, not of any notification. Option B is wrong because the notification of 1994, which first made assessment compulsory in India, has been superseded. Option D is wrong because 2010 is the year of the National Green Tribunal Act, which created the forum for appeals against clearance decisions, a related but separate law.

Q4.Environment & EcologyMedium

Environmental clearance for a Category A project is granted by which authority?

  1. A.State Environment Impact Assessment Authority
  2. B.Ministry of Environment, Forest and Climate Change
  3. C.Central Pollution Control Board
  4. D.National Green Tribunal
Show answer
Correct answer: B. Ministry of Environment, Forest and Climate Change

Explanation

The correct answer is B, the Ministry of Environment, Forest and Climate Change. Under the notification of 2006, a Category A project is appraised by the Expert Appraisal Committee constituted at the centre, and the ministry grants or refuses the prior environmental clearance on that committee's recommendation. Option A is wrong because the State Environment Impact Assessment Authority clears Category B projects, on the recommendation of the State Expert Appraisal Committee; swapping the two categories is the commonest error in this question. Option C is wrong because the Central Pollution Control Board sets standards and monitors pollution but grants no environmental clearance. Option D is wrong because the National Green Tribunal is an appellate and adjudicating body: it hears challenges to a clearance that has been granted or refused, and does not grant clearance itself.

Q5.Environment & EcologyMedium

Which of the following is the correct order of the stages of the environmental clearance process?

  1. A.Scoping, screening, appraisal, public consultation
  2. B.Screening, scoping, public consultation, appraisal
  3. C.Public consultation, screening, scoping, appraisal
  4. D.Screening, public consultation, scoping, appraisal
Show answer
Correct answer: B. Screening, scoping, public consultation, appraisal

Explanation

The correct answer is B, screening, scoping, public consultation, appraisal. Screening comes first and decides whether a Category B project needs a full assessment, making it B1, or does not, making it B2. Scoping follows, at which the appraisal committee issues the Terms of Reference. Public consultation comes third, with a public hearing at the site and written responses. Appraisal is last, when the committee scrutinises the report and the hearing record and recommends a decision. Option A is wrong because scoping cannot precede screening, since screening decides whether an assessment is needed at all. Option C is wrong because a public hearing is impossible before the report exists. Option D is wrong because consultation must follow scoping, as the hearing is held on the draft report prepared against the Terms of Reference.