Environmental clearance for a Category A project is granted by which authority?
- A.State Environment Impact Assessment Authority
- B.Ministry of Environment, Forest and Climate Change
- C.Central Pollution Control Board
- D.National Green Tribunal
Correct answer
Explanation
The correct answer is B, the Ministry of Environment, Forest and Climate Change. Under the notification of 2006, a Category A project is appraised by the Expert Appraisal Committee constituted at the centre, and the ministry grants or refuses the prior environmental clearance on that committee's recommendation. Option A is wrong because the State Environment Impact Assessment Authority clears Category B projects, on the recommendation of the State Expert Appraisal Committee; swapping the two categories is the commonest error in this question. Option C is wrong because the Central Pollution Control Board sets standards and monitors pollution but grants no environmental clearance. Option D is wrong because the National Green Tribunal is an appellate and adjudicating body: it hears challenges to a clearance that has been granted or refused, and does not grant clearance itself.
Read the full article: Environmental Impact Assessment: Process and Categories
Practice Questions
View allWhich country was the first to make Environmental Impact Assessment a statutory requirement?
- A.United Kingdom
- B.United States of America
- C.Sweden
- D.India
Show answer
The National Environmental Policy Act of 1969, which came into force in 1970, required every agency of the American federal government to prepare a statement of the environmental effects of any major action it proposed, and that requirement is taken as the beginning of environmental impact assessment as a legal…
Read the full explanation →The Environmental Impact Assessment Notification in India is issued under which Act?
- A.Wild Life (Protection) Act, 1972
- B.Water (Prevention and Control of Pollution) Act, 1974
- C.Environment (Protection) Act, 1986
- D.Forest (Conservation) Act, 1980
Show answer
Section 3 of that Act gives the central government power to take all measures it thinks necessary to protect and improve the quality of the environment, and the EIA Notifications of 1994 and 2006 were both issued under it.
Read the full explanation →The Environmental Impact Assessment Notification currently in force in India was issued in which year?
- A.1986
- B.1994
- C.2006
- D.2010
Show answer
The EIA Notification of 2006 replaced the earlier notification of 1994 and reorganised the whole clearance process, chiefly by dividing projects into Category A, appraised and cleared at the central level, and Category B, appraised and cleared at the state level, and by laying down the four stages of screening…
Read the full explanation →Which of the following is the correct order of the stages of the environmental clearance process?
- A.Scoping, screening, appraisal, public consultation
- B.Screening, scoping, public consultation, appraisal
- C.Public consultation, screening, scoping, appraisal
- D.Screening, public consultation, scoping, appraisal
Show answer
Screening comes first and decides whether a Category B project needs a full assessment, making it B1, or does not, making it B2.
Read the full explanation →At which stage of the EIA process are the Terms of Reference issued?
- A.Screening
- B.Scoping
- C.Public consultation
- D.Appraisal
Show answer
Scoping is the stage at which the Expert Appraisal Committee, or the state committee for a Category B1 project, determines the Terms of Reference: the detailed list of issues, study area, seasons of data and specific concerns that the assessment must address.
Read the full explanation →