Who conducts the public hearing during the public consultation stage of the EIA process?
- A.Expert Appraisal Committee
- B.State Pollution Control Board
- C.District collector alone
- D.Ministry of Environment, Forest and Climate Change
Show answer
Explanation
The correct answer is B, the State Pollution Control Board. The notification of 2006 makes the State Pollution Control Board, or the pollution control committee in a union territory, responsible for conducting the public hearing at or near the site of the project, for recording the proceedings and for sending that record to the appraisal committee. Option A is wrong because the Expert Appraisal Committee issues the Terms of Reference and later appraises the report, but does not hold the hearing. Option C is wrong because although the district administration assists and a senior district officer presides over the proceedings, the responsibility for conducting the hearing rests with the board. Option D is wrong because the ministry takes the final decision on a Category A project and does not conduct hearings at project sites.