Environment & Ecology Quiz: Environmental Impact Assessment

  • 11 questions
  • 11 minutes
  • Difficulty: Medium
Start Quiz

About this quiz

This Environment & Ecology quiz on Environmental Impact Assessment puts 11 multiple-choice questions to you, the verified MCQs published with GK24's note on the topic. Every question carries a full explanation of why the correct option is right and why the other options are wrong, so you learn the fact behind the answer rather than the letter. Attempt it right after reading the note, keep to the timer, and use the explanations at the end to mark what needs another look. Sit it again before the exam as a quick revision of the topic.

Questions in this quiz

11 questions with answers and explanations

Q1.Environment & EcologyMedium

Which country was the first to make Environmental Impact Assessment a statutory requirement?

  1. A.United Kingdom
  2. B.United States of America
  3. C.Sweden
  4. D.India
Show answer
Correct answer: B. United States of America

The National Environmental Policy Act of 1969, which came into force in 1970, required every agency of the American federal government to prepare a statement of the environmental effects of any major action it proposed, and that requirement is taken as the beginning of environmental impact assessment as a legal…

Q2.Environment & EcologyEasy

The Environmental Impact Assessment Notification in India is issued under which Act?

  1. A.Wild Life (Protection) Act, 1972
  2. B.Water (Prevention and Control of Pollution) Act, 1974
  3. C.Environment (Protection) Act, 1986
  4. D.Forest (Conservation) Act, 1980
Show answer
Correct answer: C. Environment (Protection) Act, 1986

Section 3 of that Act gives the central government power to take all measures it thinks necessary to protect and improve the quality of the environment, and the EIA Notifications of 1994 and 2006 were both issued under it.

Q3.Environment & EcologyEasy

The Environmental Impact Assessment Notification currently in force in India was issued in which year?

  1. A.1986
  2. B.1994
  3. C.2006
  4. D.2010
Show answer
Correct answer: C. 2006

The EIA Notification of 2006 replaced the earlier notification of 1994 and reorganised the whole clearance process, chiefly by dividing projects into Category A, appraised and cleared at the central level, and Category B, appraised and cleared at the state level, and by laying down the four stages of screening…

Q4.Environment & EcologyMedium

Environmental clearance for a Category A project is granted by which authority?

  1. A.State Environment Impact Assessment Authority
  2. B.Ministry of Environment, Forest and Climate Change
  3. C.Central Pollution Control Board
  4. D.National Green Tribunal
Show answer
Correct answer: B. Ministry of Environment, Forest and Climate Change

Under the notification of 2006, a Category A project is appraised by the Expert Appraisal Committee constituted at the centre, and the ministry grants or refuses the prior environmental clearance on that committee's recommendation.

Q5.Environment & EcologyMedium

Which of the following is the correct order of the stages of the environmental clearance process?

  1. A.Scoping, screening, appraisal, public consultation
  2. B.Screening, scoping, public consultation, appraisal
  3. C.Public consultation, screening, scoping, appraisal
  4. D.Screening, public consultation, scoping, appraisal
Show answer
Correct answer: B. Screening, scoping, public consultation, appraisal

Screening comes first and decides whether a Category B project needs a full assessment, making it B1, or does not, making it B2.

Q7.Environment & EcologyMedium

Who conducts the public hearing during the public consultation stage of the EIA process?

  1. A.Expert Appraisal Committee
  2. B.State Pollution Control Board
  3. C.District collector alone
  4. D.Ministry of Environment, Forest and Climate Change
Show answer
Correct answer: B. State Pollution Control Board

The notification of 2006 makes the State Pollution Control Board, or the pollution control committee in a union territory, responsible for conducting the public hearing at or near the site of the project, for recording the proceedings and for sending that record to the appraisal committee.

Q9.Environment & EcologyEasy

An appeal against the grant of environmental clearance lies before which forum?

  1. A.Central Pollution Control Board
  2. B.National Green Tribunal
  3. C.National Biodiversity Authority
  4. D.Central Zoo Authority
Show answer
Correct answer: B. National Green Tribunal

The tribunal was created by the National Green Tribunal Act of 2010, its principal bench sits at New Delhi, and it hears appeals against the grant or refusal of environmental clearance as well as disputes under other environmental laws.

Q10.Environment & EcologyHard

In the practice of Environmental Impact Assessment, a Rapid EIA differs from a Comprehensive EIA mainly because it

  1. A.uses baseline data of one season, excluding the monsoon
  2. B.does not need an Environment Management Plan
  3. C.is prepared by the government instead of a consultant
  4. D.applies only to projects inside protected areas
Show answer
Correct answer: A. uses baseline data of one season, excluding the monsoon

A rapid assessment is based on baseline data collected over a single season other than the monsoon, which allows the study to be completed quickly, while a comprehensive assessment collects data over all the seasons of a full year and therefore captures seasonal variation in air quality, water flow and…

Q11.Environment & EcologyHard

The Leopold matrix is a technique used in Environmental Impact Assessment for

  1. A.measuring the concentration of pollutants in water
  2. B.identifying and rating the interaction between project activities and environmental factors
  3. C.estimating the cost of mitigation measures
  4. D.mapping the boundaries of eco-sensitive zones
Show answer
Correct answer: B. identifying and rating the interaction between project activities and environmental factors

The Leopold matrix is the best known of the matrix methods: the activities of a project are set along one axis and the components of the environment along the other, and each cell where an activity meets a component is marked for the magnitude and the importance of the impact.