Skip to content
GK24
NationalEasy

How many tunnels are there on the Sivok-Rangpo new line railway project, in all of which excavation is now complete?

  1. A.10 tunnels
  2. B.14 tunnels
  3. C.23 tunnels
  4. D.45 tunnels

Correct answer

B. 14 tunnels

Explanation

The correct answer is 14 tunnels. The breakthrough in Tunnel No. 10, the longest on the alignment at 5.3 km, completed the excavation of all 14 tunnels on the project, which is why Railways described it as a major milestone for rail connectivity to Sikkim. Option A confuses the number of tunnels with the number of the particular tunnel that was holed through, Tunnel No. 10. Option C is the number of bridges on the project, not tunnels, and is a classic swap in questions of this kind. Option D is the route length in kilometres of the broad gauge line, which runs 45 km through Darjeeling and Kalimpong districts in West Bengal and Pakyong district in Sikkim. Remember also that tunnels make up about 86 per cent of the route length.

Read the full article: Sivok-Rangpo Rail Line: Excavation Done in All 14 Tunnels

Q2.NationalMedium

Roughly what share of the Sivok-Rangpo route length is made up of tunnels?

  1. A.About 45 per cent
  2. B.About 60 per cent
  3. C.About 86 per cent
  4. D.About 95 per cent
Show answer
Correct answer: C. About 86 per cent

The line traverses geographically challenging Himalayan mountain terrain, and its 14 tunnels account for roughly 86 per cent of the total route length, an unusually high proportion that explains why the completion of tunnelling is the decisive engineering step on this project.