Sivok-Rangpo Rail Line: Excavation Done in All 14 Tunnels

Indian Railways completed excavation of the 5.3-km Tunnel No. 10 on the Sivok-Rangpo new line, finishing work in all 14 tunnels on the route to Sikkim.

By Published · Updated · 2 min read
Sivok-Rangpo Rail Line: Excavation Done in All 14 Tunnels

Why in News

On 27 November 2026 Indian Railways completed excavation of the 5.3-km Tunnel No. 10 on the Sivok-Rangpo new line, finishing the digging of all 14 tunnels and taking Sikkim a step closer to its first railway link.

Indian Railways finished excavating Tunnel No. 10, the longest tunnel on the Sivok-Rangpo new line railway project, on 27 November 2026. At 5.3 km, the tunnel is the longest of the 14 on the alignment, and with it the digging of all 14 tunnels is now complete, bringing Sikkim nearer to its first rail link.

How the tunnel was dug

Excavation of Tunnel No. 10 was driven from both portals and through two access tunnels. The two faces have now met, closing the excavation stage. What remains is tunnel lining, track laying and the fitting of the essential railway safety systems before trains can run.

The project at a glance

ItemDetail
ProjectSivok-Rangpo broad gauge new line
Route length45 km
Tunnels14, excavation complete in all
Longest tunnelTunnel No. 10, 5.3 km
Share of route in tunnelsAbout 86 per cent
Bridges23
StationsSivok, Riyang, Melli and Rangpo
Underground haltTeesta Bazaar

Where the line runs

The 45-km broad gauge alignment passes through the Darjeeling and Kalimpong districts of West Bengal and the Pakyong district of Sikkim. Because it crosses difficult Himalayan mountain country, tunnels account for roughly 86 per cent of its total length, an unusually high share for an Indian line. Besides the 14 tunnels there are 23 bridges. Trains will serve Sivok, Riyang, Melli and Rangpo, with an underground halt at Teesta Bazaar. At the Sivok end the new line meets the existing New Jalpaiguri-Alipurduar route, which is how Sikkim will be joined to the national railway network.

Why it matters

Once services begin, the Sivok-Rangpo line will give Sikkim direct railway connectivity for the first time. For residents and for tourists it offers a safer, quicker and more dependable option than National Highway 10, the road the state now depends on. Railways expects the link to ease the movement of essential goods, widen market access for local businesses and lift tourism in the state. Sikkim is at present the only state in the region without a railway station of its own, so the completion of tunnelling is read as the decisive engineering milestone on the project, with the civil and track works that follow being comparatively routine in such terrain.

Important Facts

ProjectSivok-Rangpo broad gauge new line railway project
MilestoneExcavation completed in all 14 tunnels on 27 November 2026
Longest tunnelTunnel No. 10, 5.3 km
Route length45 km
Tunnel share of routeAbout 86 per cent
Bridges23
StationsSivok, Riyang, Melli, Rangpo
Underground haltTeesta Bazaar
Districts coveredDarjeeling and Kalimpong (West Bengal), Pakyong (Sikkim)
Connects withNew Jalpaiguri-Alipurduar route at Sivok
Road alternative todayNational Highway 10

Exam Point of View

Remember the project (Sivok-Rangpo new broad gauge line), its length (45 km), the number of tunnels (14) and bridges (23), the longest tunnel (No. 10, 5.3 km), the tunnel share of the route (about 86 per cent), the districts crossed (Darjeeling and Kalimpong in West Bengal, Pakyong in Sikkim), the four stations, the underground halt at Teesta Bazaar and the junction with the New Jalpaiguri-Alipurduar route at Sivok.

Practice Questions

Q3.NationalMedium

Roughly what share of the Sivok-Rangpo route length is made up of tunnels?

  1. A.About 45 per cent
  2. B.About 60 per cent
  3. C.About 86 per cent
  4. D.About 95 per cent
Show answer
Correct answer: C. About 86 per cent

The line traverses geographically challenging Himalayan mountain terrain, and its 14 tunnels account for roughly 86 per cent of the total route length, an unusually high proportion that explains why the completion of tunnelling is the decisive engineering step on this project.

Frequently Asked Questions

Which tunnel of the Sivok-Rangpo project was completed on 27 November 2026?

Excavation of Tunnel No. 10, the longest tunnel on the alignment at 5.3 km, was completed. It was dug from both ends and through two access tunnels, and with it excavation is finished in all 14 tunnels of the project.

How long is the Sivok-Rangpo railway line and where does it run?

It is a 45-km broad gauge new line running through the Darjeeling and Kalimpong districts of West Bengal and the Pakyong district of Sikkim. Tunnels account for about 86 per cent of the route and there are 23 bridges.

Why is the Sivok-Rangpo line important for Sikkim?

It will give Sikkim direct railway connectivity for the first time, joining the national network through the New Jalpaiguri-Alipurduar route at Sivok. It offers a safer and faster alternative to National Highway 10 and is expected to help the movement of essential goods and boost tourism.