Skip to content
GK24
EnvironmentMedium

What is the total project outlay approved for the Green Energy Corridor Phase-III scheme?

  1. A.Rs 54,082 crore
  2. B.Rs 1,36,378 crore
  3. C.Rs 1,86,405 crore
  4. D.Rs 2,50,000 crore

Correct answer

C. Rs 1,86,405 crore

Explanation

The correct answer is Rs 1,86,405 crore, the full outlay approved for the scheme. Option A is wrong because Rs 54,082 crore is the Central Financial Support inside that outlay, the money that offsets intra-state transmission charges and so keeps power costs down for consumers. Option B is wrong because Rs 1,36,378 crore is only the transmission slice, meant for developing Intra-State Transmission Systems under the scheme. Option D is wrong because no such figure belongs to this approval. The remaining Rs 50,000 crore of the outlay pays for 50 GWh of Battery Energy Storage Systems. The whole scheme is targeted to be in place by financial year 2032-33, with the Ministry of New and Renewable Energy steering it and State Transmission Utilities acting as the overall implementing agency.

Read the full article: Cabinet Clears Green Energy Corridor Phase-III With 50 GWh Storage

Q2.EnvironmentMedium

Under GEC-III, greenfield intra-state transmission projects will be implemented through which route?

  1. A.Tariff Based Competitive Bidding
  2. B.Cost Plus Basis
  3. C.Nomination to central public sector undertakings
  4. D.Swiss challenge method
Show answer
Correct answer: A. Tariff Based Competitive Bidding

Every greenfield project under the transmission component of GEC-III goes through this route, with Transmission Service Providers taking part on a Build-Own-Operate-Maintain model, abbreviated BOOM.

Q3.EnvironmentMedium

The Green Energy Corridor Phase-III scheme is expected to support which national capacity target?

  1. A.500 GW installed non-fossil capacity by 2030
  2. B.900 GW installed non-fossil capacity by 2035
  3. C.450 GW installed solar capacity by 2040
  4. D.1,200 GW installed renewable capacity by 2047
Show answer
Correct answer: B. 900 GW installed non-fossil capacity by 2035

The scheme is described as an aid to reaching that target, since new renewable capacity is of little use unless the power it makes can be carried to load centres.

Q5.EnvironmentMedium

PAVAN, which brings air quality, emission, weather, satellite and compliance data onto one platform, belongs to which body?

  1. A.India Meteorological Department
  2. B.Commission for Air Quality Management
  3. C.National Green Tribunal
  4. D.Municipal Corporation of Delhi
Show answer
Correct answer: B. Commission for Air Quality Management

PAVAN stands for the Platform for Air Quality Vigilance and Analytics for NCR, and it is CAQM’s own platform, built so that air quality readings, emission data, meteorological information, satellite inputs and compliance records can be seen together instead of in separate silos.