The Green Energy Corridor Phase-III scheme is expected to support which national capacity target?
- A.500 GW installed non-fossil capacity by 2030
- B.900 GW installed non-fossil capacity by 2035
- C.450 GW installed solar capacity by 2040
- D.1,200 GW installed renewable capacity by 2047
Correct answer
Explanation
The correct answer is 900 GW installed non-fossil capacity by 2035. The scheme is described as an aid to reaching that target, since new renewable capacity is of little use unless the power it makes can be carried to load centres. Options A, C and D name other combinations of capacity and year that are not part of this decision, and each mixes up either the quantity or the deadline. Beyond the capacity goal, the government expects GEC-III to add to long-term energy security and cut the country's carbon footprint. It is also presented as a source of employment: direct and indirect jobs in the power, manufacturing and construction sectors, fresh work in the domestic energy storage industry as batteries are made and installed, and lasting skilled jobs in operation, maintenance and grid management in the participating states.
Read the full article: Cabinet Clears Green Energy Corridor Phase-III With 50 GWh Storage
Practice Questions
How much renewable energy is the Green Energy Corridor Phase-III scheme designed to help evacuate across states and union territories?
- A.Up to 85 GW
- B.Up to 135 GW
- C.Up to 250 GW
- D.Up to 500 GW
Show answer
GEC-III strengthens the Intra-State Transmission System precisely so that renewable power of this scale can be moved from where it is generated into the grid inside states and union territories.
Read the full explanation →What is the total project outlay approved for the Green Energy Corridor Phase-III scheme?
- A.Rs 54,082 crore
- B.Rs 1,36,378 crore
- C.Rs 1,86,405 crore
- D.Rs 2,50,000 crore
Show answer
The correct answer is Rs 1,86,405 crore, the full outlay approved for the scheme.
Read the full explanation →Under GEC-III, greenfield intra-state transmission projects will be implemented through which route?
- A.Tariff Based Competitive Bidding
- B.Cost Plus Basis
- C.Nomination to central public sector undertakings
- D.Swiss challenge method
Show answer
Every greenfield project under the transmission component of GEC-III goes through this route, with Transmission Service Providers taking part on a Build-Own-Operate-Maintain model, abbreviated BOOM.
Read the full explanation →In the road dust review, how much of the targeted road length in NCR had been redeveloped?
- A.3,221 km of 5,480 km
- B.5,480 km of 6,747 km
- C.2,298 km of 3,221 km
- D.2,345 km of 5,480 km
Show answer
Road-owning agencies were told to give priority to repairing potholes, damaged footpaths and central verges and to pave roads end to end as the CAQM framework requires, backed by surveys using artificial intelligence.
Read the full explanation →PAVAN, which brings air quality, emission, weather, satellite and compliance data onto one platform, belongs to which body?
- A.India Meteorological Department
- B.Commission for Air Quality Management
- C.National Green Tribunal
- D.Municipal Corporation of Delhi
Show answer
PAVAN stands for the Platform for Air Quality Vigilance and Analytics for NCR, and it is CAQM’s own platform, built so that air quality readings, emission data, meteorological information, satellite inputs and compliance records can be seen together instead of in separate silos.
Read the full explanation →