Skip to content
GK24
EnvironmentMedium

Under GEC-III, greenfield intra-state transmission projects will be implemented through which route?

  1. A.Tariff Based Competitive Bidding
  2. B.Cost Plus Basis
  3. C.Nomination to central public sector undertakings
  4. D.Swiss challenge method

Correct answer

A. Tariff Based Competitive Bidding

Explanation

The correct answer is Tariff Based Competitive Bidding, usually written as TBCB. Every greenfield project under the transmission component of GEC-III goes through this route, with Transmission Service Providers taking part on a Build-Own-Operate-Maintain model, abbreviated BOOM. Option B is wrong because the Cost Plus Basis is reserved for a different class of work, namely brownfield upgradation and jobs that strengthen an existing network. Option C is wrong because the scheme does not hand greenfield work to any undertaking by nomination; State Transmission Utilities are the overall implementing agency, but the projects themselves are bid out. Option D is wrong because no such method is part of this approval. The competitive route is one reason the government expects the scheme to keep transmission charges, and therefore consumer tariffs, in check.

Read the full article: Cabinet Clears Green Energy Corridor Phase-III With 50 GWh Storage

Q3.EnvironmentMedium

The Green Energy Corridor Phase-III scheme is expected to support which national capacity target?

  1. A.500 GW installed non-fossil capacity by 2030
  2. B.900 GW installed non-fossil capacity by 2035
  3. C.450 GW installed solar capacity by 2040
  4. D.1,200 GW installed renewable capacity by 2047
Show answer
Correct answer: B. 900 GW installed non-fossil capacity by 2035

The scheme is described as an aid to reaching that target, since new renewable capacity is of little use unless the power it makes can be carried to load centres.

Q5.EnvironmentMedium

PAVAN, which brings air quality, emission, weather, satellite and compliance data onto one platform, belongs to which body?

  1. A.India Meteorological Department
  2. B.Commission for Air Quality Management
  3. C.National Green Tribunal
  4. D.Municipal Corporation of Delhi
Show answer
Correct answer: B. Commission for Air Quality Management

PAVAN stands for the Platform for Air Quality Vigilance and Analytics for NCR, and it is CAQM’s own platform, built so that air quality readings, emission data, meteorological information, satellite inputs and compliance records can be seen together instead of in separate silos.