Which pillar of the new VB-G RAM G Schedule carries the highest number of permissible works?
- A.Water Security
- B.Core Rural Infrastructure
- C.Livelihood-related Infrastructure
- D.Disaster Preparedness
Correct answer
A. Water Security
Explanation
The correct answer is Water Security, which carries 128 works and is the largest of the four pillars. It covers check dams, gully plugs, underground dykes, recharge shafts, injection wells, the revival of rivers and nallahs, the reclaiming of waterlogged land, drip irrigation, sprinklers, rooftop rainwater harvesting and even ice-stupas and artificial glaciers. Option B is wrong because Core Rural Infrastructure has 111 works, which is second. Option C is wrong because Livelihood-related Infrastructure has 98 works, although its share of the list has risen sharply. Option D is wrong because Disaster Preparedness has 38 works and is the smallest of the four, even though it is the first time such a head has been given a place of its own in the rural works list. The descending order is 128, 111, 98 and 38.
Read the full article: VB-G RAM G Schedule Notifies 375 Permissible Rural Works
Practice Questions
How many permissible works have been notified under the new Schedule of the VB-G RAM G Act?
- A.266
- B.300
- C.375
- D.425
Show answer
Correct answer: C. 375
Explanation
The correct answer is 375. The Ministry of Rural Development has notified a Schedule of Permissible Works allowing that many works under the new rural works framework of the VB-G RAM G Act. Option A is the trap, because 266 is the number of works the earlier framework carried; the new list is 41 per cent wider than that, which is how the figure of 375 is arrived at. Option B is a round number that appears nowhere in the notification. Option D is higher than the figure actually notified and is placed there to catch a candidate who remembers only that the list grew. Keep the pair of numbers together, the old count and the new one, with the percentage rise between them, because questions are set on all three. So the right choice is 375 works.
The Schedule of Permissible Works has been notified under the VB-G RAM G Act of which year?
- A.2023
- B.2024
- C.2025
- D.2026
Show answer
Correct answer: C. 2025
Explanation
The correct answer is 2025. The Ministry of Rural Development notified the Schedule of Permissible Works under the Viksit Bharat - Guarantee for Rozgar and Ajeevika Mission (Gramin) Act of that year, and the Schedule itself was put out on 6 October 2026. Options A and B name years before the Act and are wrong. Option D is the tempting one, because the notification of the Schedule came in that year; but the question asks for the year of the Act, not the year of the notification, and the two are a year apart. Candidates should fix the sequence in mind: the Act belongs to 2025, the Schedule of 375 permissible works was notified in 2026, and the whole effort is placed within the goal of a Viksit Bharat by 2047. Mixing the three years is the commonest mistake here.
Under VB-G RAM G, through which plan will works be taken up, and who approves it?
- A.District Development Plan, approved by the Zila Parishad
- B.Viksit Gram Panchayat Plan, approved by the Gram Sabha
- C.Block Action Plan, approved by the Block Samiti
- D.State Rural Plan, approved by the State Legislature
Show answer
Correct answer: B. Viksit Gram Panchayat Plan, approved by the Gram Sabha
Explanation
The correct answer is the Viksit Gram Panchayat Plan, approved by the Gram Sabha. Every work under the new framework is to begin from the bottom up through a decentralised planning exercise, and the plan must be cleared by the Gram Sabha before a work can start. Each work is then followed on the Viksit Bharat National Rural Infrastructure Stack, a digital trail meant to bring Central, State and local money onto the same work and to stop the same work being taken up twice. Options A, C and D place the power of approval at the district, block and State level respectively, which runs against the village-level, bottom-up design the Schedule sets out. The point to remember is the pair: planning at the Gram Panchayat, approval by the Gram Sabha, tracking on the national stack.
What is the share of women in the total utilisation of eSanjeevani?
- A.16.25 per cent
- B.40.15 per cent
- C.47.14 per cent
- D.57.14 per cent
Show answer
Correct answer: D. 57.14 per cent
Explanation
The correct answer is 57.14 per cent. Women make up that share of all use of eSanjeevani, which shows how far telemedicine has gone in reaching people for whom a journey to a health facility means time, money and difficulty. Option B, 40.15 per cent, is the share of consultations taken by citizens of 46 years and above, so it belongs to an age group and not to women. Option A, 16.25 per cent, is the share of senior citizens of 60 years and above, who form part of that same older group. Option C is close to the right figure in look but is not the one reported, and it is the sort of near miss a paper setter puts in to catch a half-remembered number. Candidates should hold the three shares together, because questions often swap one for another.
Which organisation developed the eSanjeevani digital health platform?
- A.Centre for Development of Advanced Computing (C-DAC)
- B.National Informatics Centre (NIC)
- C.Indian Space Research Organisation (ISRO)
- D.Council of Scientific and Industrial Research (CSIR)
Show answer
Correct answer: A. Centre for Development of Advanced Computing (C-DAC)
Explanation
The correct answer is the Centre for Development of Advanced Computing (C-DAC). eSanjeevani is described as a made-in-India digital health solution developed by C-DAC, and its Mohali centre has given end-to-end technological development and engineering support from the very beginning. The platform grew from a hub-and-spoke telemedicine model into a national digital health platform of population scale. Option B is wrong because the National Informatics Centre is not named as the developer of this platform. Option C is wrong because the Indian Space Research Organisation works on space missions and satellites, not on a telemedicine service of this kind. Option D is wrong because the Council of Scientific and Industrial Research runs a chain of research laboratories and has no role described here. Remembering the pair, C-DAC and C-DAC Mohali, is enough for most questions on this story.