Which body appraises public-private partnership projects of the central sector and is chaired by the Secretary, Department of Economic Affairs?

  1. A.Public Private Partnership Appraisal Committee
  2. B.Cabinet Committee on Economic Affairs
  3. C.Governing Council of NITI Aayog
  4. D.Finance Commission of India

Correct answer

A. Public Private Partnership Appraisal Committee

Explanation

The correct answer is A, the Public Private Partnership Appraisal Committee, usually written as PPPAC. It is the standing inter-ministerial committee that examines the concession agreement, the risk sharing and the financial structure of a central sector PPP proposal before approval, and its chair is the Secretary of the Department of Economic Affairs, with the secretaries of Expenditure, Legal Affairs, NITI Aayog and the sponsoring ministry as members. B, the Cabinet Committee on Economic Affairs, takes the final political decision on large projects but does not perform the technical appraisal. C is the body of chief ministers that guides NITI Aayog and has no project clearance role. D is a constitutional body under Article 280 that recommends the sharing of taxes between the Union and the States.

Read the full article: Infrastructure and PPP: Models, VGF and Master Plans

View all
Q1.Indian EconomyAsked in: Uttar Pradesh · UPPSC Civil Services General Studies OffMedium

Given below are two statements, one labelled as Assertion (A) and the other as Reason (R). Assertion (A): Government has launched the National Infrastructure Pipeline (NIP) for the period of 2020-30. Reason (R): The objective of NIP is to provide equitable access to infrastructure for all. Select the correct answer using the codes given below.

  1. A.Both (A) and (R) are true and (R) is the correct explanation of (A)
  2. B.Both (A) and (R) are true but (R) is not the correct explanation of (A)
  3. C.(A) is true but (R) is false
  4. D.(A) is false but (R) is true
Show answer
Correct answer: D. (A) is false but (R) is true

Explanation

The correct answer is D, (A) is false but (R) is true. The National Infrastructure Pipeline was announced in the Budget speech of 2019-20 and the task force under the Secretary, Department of Economic Affairs, drew it up for the five years from 2019-20 to 2024-25, with projected capital expenditure of about 111 lakh crore rupees. The period in the assertion, 2020-30, is therefore wrong, which rules out A and B, both of which treat the assertion as true. The reason, however, states the pipeline aim correctly: the NIP report sets out to give every citizen equitable access to world-class infrastructure, and that purpose is genuine. C is wrong because it reverses the position, calling the false assertion true and the true reason false. Read such pairs by testing the assertion first, because a false assertion settles the answer at once.

Q2.Indian EconomyMedium

In the Hybrid Annuity Model used for national highway projects, what share of the project cost is provided by the government as a grant during construction?

  1. A.20 per cent
  2. B.40 per cent
  3. C.60 per cent
  4. D.100 per cent
Show answer
Correct answer: B. 40 per cent

Explanation

The correct answer is B, 40 per cent. The Hybrid Annuity Model was adopted to revive road construction after both the toll and the annuity models ran into trouble. The authority releases forty per cent of the bid project cost as a construction grant in instalments while the work proceeds, and the concessionaire raises the remaining sixty per cent from its own funds and from lenders. That sixty per cent is returned after completion as a series of annuities with interest linked to a bank rate, and the toll is collected by the authority itself. A, twenty per cent, is the ceiling for central viability gap funding, not the HAM grant. C, sixty per cent, is the share the concessionaire brings, so the option inverts the split. D would make it an EPC contract rather than a partnership.

Q3.Indian EconomyMedium

Under the Viability Gap Funding scheme, the capital grant from the Central Government is normally limited to what share of the total project cost?

  1. A.10 per cent
  2. B.20 per cent
  3. C.40 per cent
  4. D.50 per cent
Show answer
Correct answer: B. 20 per cent

Explanation

The correct answer is B, 20 per cent. Viability Gap Funding is a one-time or deferred capital grant for a project that is economically necessary but commercially unviable, such as a rural road or a water supply line whose user charges can never repay the capital. The Department of Economic Affairs gives up to twenty per cent of the project cost, and the sponsoring ministry, State government or statutory authority may give a further twenty per cent, so support can reach forty per cent in total. That is why C is a tempting distractor: forty per cent is the combined ceiling, not the central share alone. A understates the scheme, and D is not available under it at all. Remember the pair of figures as twenty plus twenty.

Q4.Indian EconomyMedium

In the Toll-Operate-Transfer (TOT) model, what exactly is handed over to the private operator?

  1. A.A greenfield expressway that is still under construction
  2. B.An operating national highway stretch that already collects toll
  3. C.A plot of land for building a logistics park
  4. D.A railway line owned by a State government
Show answer
Correct answer: B. An operating national highway stretch that already collects toll

Explanation

The correct answer is B, an operating national highway stretch that already collects toll. Under TOT the authority bundles completed highway sections that have a proven traffic record and auctions the right to collect toll on them for a long concession, usually thirty years, against a single upfront payment. The money so received is used to build new roads, so TOT is a monetisation tool rather than a construction model, and the asset returns to the authority at the end. A describes a greenfield concession such as BOT or HAM, where the road has yet to be built and the traffic is only a forecast. C is a land lease, not a toll concession. D is outside the scheme, which covers national highways held by the central authority.

Q5.Indian EconomyEasy

Which of the following is NOT a public-private partnership model?

  1. A.BOT (Annuity)
  2. B.Hybrid Annuity Model
  3. C.Engineering, Procurement and Construction
  4. D.Design, Build, Finance, Operate and Transfer
Show answer
Correct answer: C. Engineering, Procurement and Construction

Explanation

The correct answer is C, Engineering, Procurement and Construction. In an EPC contract the government owns the project, funds it from its own budget and simply buys construction services; the contractor is paid for the work done, keeps no operating responsibility and takes no revenue risk, so none of the defining features of a partnership is present. A, BOT on annuity, is a partnership in which the private partner builds with its own finance and is repaid in fixed instalments. B, the Hybrid Annuity Model, mixes a forty per cent construction grant with private finance for the rest. D, DBFOT, is the fullest form of concession, where the private partner designs, finances, builds, operates and finally transfers the asset. Examiners use this question to test the single idea that private finance and operation make a PPP.