Given below are two statements, one labelled as Assertion (A) and the other as Reason (R). Assertion (A): Government has launched the National Infrastructure Pipeline (NIP) for the period of 2020-30. Reason (R): The objective of NIP is to provide equitable access to infrastructure for all. Select the correct answer using the codes given below.

  1. A.Both (A) and (R) are true and (R) is the correct explanation of (A)
  2. B.Both (A) and (R) are true but (R) is not the correct explanation of (A)
  3. C.(A) is true but (R) is false
  4. D.(A) is false but (R) is true

Correct answer

D. (A) is false but (R) is true

Explanation

The correct answer is D, (A) is false but (R) is true. The National Infrastructure Pipeline was announced in the Budget speech of 2019-20 and the task force under the Secretary, Department of Economic Affairs, drew it up for the five years from 2019-20 to 2024-25, with projected capital expenditure of about 111 lakh crore rupees. The period in the assertion, 2020-30, is therefore wrong, which rules out A and B, both of which treat the assertion as true. The reason, however, states the pipeline aim correctly: the NIP report sets out to give every citizen equitable access to world-class infrastructure, and that purpose is genuine. C is wrong because it reverses the position, calling the false assertion true and the true reason false. Read such pairs by testing the assertion first, because a false assertion settles the answer at once.

Read the full article: Infrastructure and PPP: Models, VGF and Master Plans

View all
Q2.Indian EconomyMedium

Under the Viability Gap Funding scheme, the capital grant from the Central Government is normally limited to what share of the total project cost?

  1. A.10 per cent
  2. B.20 per cent
  3. C.40 per cent
  4. D.50 per cent
Show answer
Correct answer: B. 20 per cent

Viability Gap Funding is a one-time or deferred capital grant for a project that is economically necessary but commercially unviable, such as a rural road or a water supply line whose user charges can never repay the capital.

Q3.Indian EconomyHard

Which body appraises public-private partnership projects of the central sector and is chaired by the Secretary, Department of Economic Affairs?

  1. A.Public Private Partnership Appraisal Committee
  2. B.Cabinet Committee on Economic Affairs
  3. C.Governing Council of NITI Aayog
  4. D.Finance Commission of India
Show answer
Correct answer: A. Public Private Partnership Appraisal Committee

It is the standing inter-ministerial committee that examines the concession agreement, the risk sharing and the financial structure of a central sector PPP proposal before approval, and its chair is the Secretary of the Department of Economic Affairs, with the secretaries of Expenditure, Legal Affairs, NITI Aayog and the sponsoring…

Q4.Indian EconomyMedium

In the Toll-Operate-Transfer (TOT) model, what exactly is handed over to the private operator?

  1. A.A greenfield expressway that is still under construction
  2. B.An operating national highway stretch that already collects toll
  3. C.A plot of land for building a logistics park
  4. D.A railway line owned by a State government
Show answer
Correct answer: B. An operating national highway stretch that already collects toll

Under TOT the authority bundles completed highway sections that have a proven traffic record and auctions the right to collect toll on them for a long concession, usually thirty years, against a single upfront payment.

Q5.Indian EconomyEasy

Which of the following is NOT a public-private partnership model?

  1. A.BOT (Annuity)
  2. B.Hybrid Annuity Model
  3. C.Engineering, Procurement and Construction
  4. D.Design, Build, Finance, Operate and Transfer
Show answer
Correct answer: C. Engineering, Procurement and Construction

In an EPC contract the government owns the project, funds it from its own budget and simply buys construction services; the contractor is paid for the work done, keeps no operating responsibility and takes no revenue risk, so none of the defining features of a partnership is present.