Skip to content
GK24
NationalMedium

Under the amended rules, interconnection shifts to which level?

  1. A.Short Distance Charging Area (SDCA) level
  2. B.Long Distance Charging Area (LDCA) level
  3. C.Licensed Service Area (LSA) level
  4. D.District level

Correct answer

C. Licensed Service Area (LSA) level

Explanation

The correct answer is Licensed Service Area (LSA) level. The amendment modernises the framework by moving handover and takeover of telecom traffic away from the older charging-area geography to the Licensed Service Area, and it lets the interconnection provider and seeker agree between themselves where traffic will change hands. Options A and B are wrong because the Short Distance Charging Area and Long Distance Charging Area levels are precisely what the regulations are moving away from; existing minutes of usage at such points of interconnection must be migrated to LSA-level points in phases within three years. Option D is wrong because no district-level interconnection has been prescribed. TRAI expects the change to simplify routing, make better use of scarce numbering resources, cut latency and improve service reliability.

Read the full article: TRAI Issues Telecom Interconnection Third Amendment Rules 2026

Q1.NationalEasy

From which date do the Telecommunication Interconnection (Third Amendment) Regulations, 2026 take effect?

  1. A.1 December 2026
  2. B.1 January 2027
  3. C.1 April 2027
  4. D.3 November 2026
Show answer
Correct answer: B. 1 January 2027

The Telecom Regulatory Authority of India released these amendment regulations and stated that they would come into force from the first day of January 2027, which gives operators a window to prepare before the new interconnection duties begin.

Q2.NationalHard

What is the ceiling on the interest rate for delayed payment of interconnection charges?

  1. A.RBI repo rate plus one percent
  2. B.SBI one-year MCLR plus two percent
  3. C.A flat rate of 18 percent a year
  4. D.Bank rate plus three percent
Show answer
Correct answer: B. SBI one-year MCLR plus two percent

A fresh provision now deals with late payment of interconnection charges and interconnection usage charges: the two service providers may settle the interest rate between themselves, but it cannot go above that benchmark.

Q3.NationalMedium

Existing points of interconnection running on E1 or TDM links must be migrated to IP-based interconnection within what period?

  1. A.One year
  2. B.Two years
  3. C.Three years
  4. D.Five years
Show answer
Correct answer: C. Three years

The amendment regulations provide that every interconnection established after they come into force must be IP-based, and that points of interconnection still working on E1 or TDM technology have to be converted to IP-based interconnection in a phased manner within three years.