How much was sanctioned to ten states under the Prime Minister Rashtriya Krishi Vikas Yojana at the National Agriculture Conference - Rabi Campaign 2026?
- A.More than Rs 800 crore
- B.More than Rs 1200 crore
- C.More than Rs 1800 crore
- D.More than Rs 2400 crore
Correct answer
B. More than Rs 1200 crore
Explanation
The correct answer is more than Rs 1200 crore. At the conference the Union Agriculture Minister handed financial sanction letters under PM-RKVY to the agriculture ministers of ten states, and the total came to more than Rs 1200 crore. The individual shares add up to that figure: West Bengal Rs 290 crore, Haryana Rs 198 crore, Chhattisgarh Rs 181 crore, Arunachal Pradesh Rs 154 crore, Bihar Rs 114 crore, Karnataka Rs 104 crore, Mizoram Rs 75 crore, Himachal Pradesh Rs 64 crore, Jharkhand Rs 58 crore and Punjab Rs 43 crore. Option A is too low and does not match the sum of the state shares. Option C and option D are both far above what was actually distributed and correspond to no announcement made at the conference. Candidates should also note that the money was released so that states could begin work on the ground at once rather than wait for funds after the season had started.
Read the full article: PM-RKVY: Rs 1200 Crore Sanctioned to 10 States at Rabi Meet
Practice Questions
Which state received the largest sanction among the ten states that got PM-RKVY letters at the Rabi Campaign conference?
- A.Punjab
- B.Bihar
- C.West Bengal
- D.Haryana
Show answer
Correct answer: C. West Bengal
Explanation
The correct answer is West Bengal, which was sanctioned Rs 290 crore, the biggest single share of the more than Rs 1200 crore distributed under PM-RKVY. Punjab in option A stands at the other end of the list with Rs 43 crore, the smallest of the ten sanctions announced. Bihar in option B received Rs 114 crore, well behind West Bengal, and Haryana in option D came second with Rs 198 crore. The full list also covered Chhattisgarh with Rs 181 crore, Arunachal Pradesh with Rs 154 crore, Karnataka with Rs 104 crore, Mizoram with Rs 75 crore, Himachal Pradesh with Rs 64 crore and Jharkhand with Rs 58 crore. Learning the top three and the bottom of this list is enough for most objective papers, because examiners usually ask for the highest or the lowest recipient rather than the whole table.
The nationwide Khet Bachao Abhiyan announced for soil health is to be run during which period?
- A.22 October to 30 November
- B.2 October to 31 October
- C.10 September to 17 September
- D.1 November to 31 December
Show answer
Correct answer: A. 22 October to 30 November
Explanation
The correct answer is 22 October to 30 November. The campaign was announced to protect soil health and the environment, and scientists together with other stakeholders are to take part in it. Working from Soil Health Cards, it promotes balanced use of fertiliser so that soil fertility and beneficial insects are not damaged, and it encourages pulse cultivation in the rice fallow fields of eastern India, especially Jharkhand, Bihar, Odisha and West Bengal, once paddy has been harvested. Option B names a window that belongs to a different government cleanliness campaign, not to this one. Option C repeats the dates fixed for the rabi interface meetings at district and state level, which are a separate announcement from the same conference. Option D is not a period mentioned at all. Note the pairing carefully, since the same conference produced several date-based announcements.
How many types of permissible works are identified under the Viksit Gram Panchayat Plan framework?
- A.186
- B.262
- C.318
- D.404
Show answer
Correct answer: C. 318
Explanation
The correct answer is 318. The VGPP framework identifies that many types of permissible works, spread over the four thematic areas of the mission. A Viksit Gram Panchayat Plan is prepared with the participation of the Gram Sabha, which also recommends and approves it. The process starts with an inventory of assets, infrastructure and service gaps in the panchayat, including assets built under central and state schemes, and then uses GIS along with Yuktdhara and PM Gati Shakti so that spending is not duplicated. Options A, B and D are plausible-looking counts but none of them is the figure given for permissible works. Remember also that these plans are consolidated at block, district, state and national level, and that the consolidated version feeds the Viksit Bharat National Rural Infrastructure Stack.
From which date did the VB-G RAM G Act, 2025 come into force across rural India?
- A.1 April 2026
- B.1 July 2026
- C.2 October 2026
- D.1 January 2026
Show answer
Correct answer: B. 1 July 2026
Explanation
The correct answer is 1 July 2026. The Act was passed in 2025 and was brought into force on that date, after which it was rolled out in every rural area of the country. The changeover from the earlier rural employment guarantee law was described as seamless, because the digital systems that support verification, monitoring and payment were already working when the new framework began. Option A is the start of the financial year and is a natural guess, but it is not the commencement date. Option C is a date associated with several government campaigns and anniversaries, not with this statute. Option D is the start of the calendar year and has no connection with the mission. Candidates should pair the commencement date with the progress cut-off used in the backgrounder, which reports figures as they stood on 24 September 2026.
How many days of wage employment does the VB-G RAM G Act guarantee to an eligible rural household in a financial year?
- A.100 days
- B.125 days
- C.150 days
- D.200 days
Show answer
Correct answer: B. 125 days
Explanation
The correct answer is 125 days. The law provides a statutory guarantee of wage employment for 125 days in every financial year, and the guarantee is available to every rural household whose adult members volunteer for unskilled manual work. Option A is the figure people remember from the older rural employment law that this framework has replaced, which makes it the commonest wrong choice in the paper. Option C and option D are higher than anything the statute promises and appear in no official statement about the mission. Along with the number of days, remember that the guarantee is tied to four thematic areas: water security, core rural infrastructure, livelihood-related infrastructure and protection against extreme weather events. The framework also aims at empowerment, growth, convergence and saturation, and it works through plans prepared at the gram panchayat level and approved by the Gram Sabha.