Under which mode of implementation has the four-laning of NH-22 in Bihar been approved?
- A.Engineering, Procurement and Construction
- B.Build, Operate and Transfer (Toll)
- C.Hybrid Annuity Mode
- D.Build, Own, Operate and Transfer
Show answer
This is the model under which the Cabinet Committee on Economic Affairs cleared the upgradation of the 82.57-km stretch at a total capital cost of Rs 3,590.73 crore.