What is the estimated public-private partnership cost of the second container terminal at Kamarajar Port?
- A.Rs 1,280 crore
- B.Rs 2,450 crore
- C.Rs 4,288.26 crore
- D.Rs 6,750 crore
Correct answer
Explanation
The correct answer is Rs 4,288.26 crore, a figure that includes GST. The terminal is to be developed on a Design, Build, Finance, Operate and Transfer basis under the public-private partnership model, with a concession running 40 years and construction planned over 48 months in two phases. Rs 1,280 crore is wrong: that is roughly the revenue the port reported in FY 2025-26, not the cost of the terminal, and its profit before tax that year was Rs 924 crore. Rs 2,450 crore is wrong because no such amount appears for this project. Rs 6,750 crore is wrong for the same reason. Note that Kamarajar Port Limited will separately meet an estimated Rs 450 crore for dredging, and the project is expected to create about 750 jobs while being built and about 800 once it operates.
Read the full article: Kamarajar Port to Get Second Container Terminal of 2 Mn TEUs
Practice Questions
The second container terminal approved on 25 November 2026 will come up at which port?
- A.Visakhapatnam Port
- B.Kamarajar Port
- C.Paradip Port
- D.Mormugao Port
Show answer
The approved terminal will add two million TEUs of annual capacity at an estimated public-private partnership cost of Rs 4,288.26 crore including GST, with the port bearing a further Rs 450 crore for dredging.
Read the full explanation →How much container traffic did Indian ports handle in FY 2025-26, according to the backgrounder?
- A.18.4 million TEUs
- B.25.7 million TEUs
- C.32.1 million TEUs
- D.40 million TEUs
Show answer
Container traffic across Indian ports grew at a compound annual growth rate of 6.9 per cent between FY 2019-20 and FY 2025-26 to reach that level.
Read the full explanation →The 125-km Rishikesh-Karnaprayag railway line mentioned alongside the Gangasagar project is being built in which state?
- A.Himachal Pradesh
- B.Uttar Pradesh
- C.Uttarakhand
- D.West Bengal
Show answer
The Rishikesh-Karnaprayag line, about 125 km long, is being developed through the Garhwal region of Uttarakhand; it passes through Rudraprayag district and joins Rishikesh with destinations such as Devprayag and Karnaprayag.
Read the full explanation →Gangasagar, the destination of the newly surveyed railway line, is located on which island?
- A.Majuli
- B.Sagar Island
- C.Sriharikota
- D.Diu
Show answer
Gangasagar stands on Sagar Island in West Bengal, and the new line, once built, will extend rail connectivity towards that island.
Read the full explanation →The major bridge on the approved Kakdwip-Gangasagar railway line will cross which river?
- A.Hooghly
- B.Muriganga
- C.Damodar
- D.Subarnarekha
Show answer
The new line between Kakdwip and Gangasagar will run for roughly 34 km and will include a major bridge of about 4.5 km built across the River Hooghly; that crossing is expected to be among the longest railway bridges in the country once it is complete.
Read the full explanation →