Under which article of the climate convention does India hold that providing climate finance is an obligation of developed countries?

  1. A.Article 4.2
  2. B.Article 6
  3. C.Article 9.1
  4. D.Article 12

Correct answer

C. Article 9.1

Explanation

The correct answer is Article 9.1. The Environment Minister stated that the provision of climate finance is a duty cast on developed countries by this article, and that such finance must be predictable, largely public and concessional so that it does not add to the debt burden of developing countries. India is therefore seeking a decision at the conference to commence the Climate Finance Work Programme. Options A, B and D name provisions that were not cited in the briefing for this purpose. Students should also note the parallel demand under the biodiversity convention, where India pressed developed countries to fulfil their obligations under Article 20(2) and opposed any mandatory widening of the base of contributors or any shifting of existing financial responsibility onto developing countries.

Read the full article: India Lists Climate Finance Priorities for COP31 in Antalya

Q2.EnvironmentMedium

At the seventeenth session of the desertification convention in Ulaanbaatar, India was elected to which position?

  1. A.President of the Conference of the Parties
  2. B.Chair of the Asia-Pacific Regional Group
  3. C.Chair of the Committee on Science and Technology
  4. D.Co-Chair of the Global Stocktake
Show answer
Correct answer: B. Chair of the Asia-Pacific Regional Group

At the session held in the Mongolian capital, India took that chair and then restated its pledge to restore more than 26 million hectares of degraded land by 2030, while asking for diversified, adequate and sustained international finance for restoration and for drought resilience.

Q5.EnvironmentMedium

As of August 2025, how many operational agrivoltaic projects did India have and of what installed capacity?

  1. A.26 projects of 27.54 megawatts
  2. B.36 projects of 37.54 megawatts
  3. C.46 projects of 47.54 megawatts
  4. D.36 projects of 137.54 megawatts
Show answer
Correct answer: B. 36 projects of 37.54 megawatts

That was India’s operational agrivoltaic fleet as of August 2025, and alongside it 10 pilot projects were under development. These projects are spread across different agro-climatic regions and use elevated structures, interspace layouts and tracking systems.