The Integrated Transport and Logistics Authority will undertake technical appraisal of projects costing at least how much?
- A.100 crore rupees
- B.250 crore rupees
- C.500 crore rupees
- D.1000 crore rupees
Correct answer
Explanation
The correct answer is 500 crore rupees. The Union Cabinet has approved setting up the Integrated Transport and Logistics Authority, which will take a long-term view of transport planning. It will prepare a National Transport Master Plan with a horizon of ten years or more, assess sectoral and annual transport plans, appraise projects costing 500 crore rupees or more, and monitor their implementation. The other three thresholds are plausible figures for project appraisal but none of them is the limit set for this authority. The authority will also build a National Transport Data Repository by pulling together information from sources such as FASTag, Vahan and GSTN e-way bills, which gives planners a single view of how goods and people actually move across the country.
Read the full article: PM GatiShakti at Five: 58 Ministries, 23,493 Data Layers
Practice Questions
On which date was the PM GatiShakti National Master Plan launched?
- A.13 October 2021
- B.15 August 2021
- C.13 October 2022
- D.1 April 2020
Show answer
The idea was to put data held by different ministries, states and union territories onto one Geographic Information System platform so that road, rail, port, airport, waterway and utility networks could be planned together instead of in isolation.
Read the full explanation →How many Central Ministries and Departments does the PM GatiShakti National Master Plan cover?
- A.36
- B.46
- C.58
- D.230
Show answer
The master plan brings 58 Central Ministries and Departments into a single planning framework, so that infrastructure proposals can be assessed across sectors rather than ministry by ministry.
Read the full explanation →How many data layers did the PM GatiShakti National Master Plan carry as of 12 October 2026?
- A.3,964
- B.12,560
- C.23,493
- D.58,000
Show answer
That is the number of data layers on the common Geographic Information System platform as of 12 October 2026, covering infrastructure assets and other information that planners need when they fix an alignment or test a site.
Read the full explanation →Which body will act as the training partner for the Nal Jal Mitra programme, handling coordination, assessment, certification and fund disbursement?
- A.CSTARI
- B.NCVET
- C.National Instructional Media Institute
- D.National Jal Jeevan Mission
Show answer
It will serve as training partner for coordination of training, assessment, certification and the release of funds.
Read the full explanation →What is the total duration of the Nal Jal Mitra short-term training course?
- A.120 hours
- B.145 hours
- C.165 hours
- D.180 hours
Show answer
The course is split into 120 hours of institutional training, covering both theory and practical work, and 45 hours of compulsory on-the-job training at functioning rural piped water supply schemes.