How many pillars does the Data Centre Evaluation Framework rest on?
- A.Three
- B.Four
- C.Five
- D.Seven
Correct answer
Explanation
The correct answer is five. The framework is built around Power and Energy; Water and Cooling; Siting and Environmental Sustainability; Economic and Strategic Value; and Policy, Governance and Implementation. Under these heads it asks States to check grid readiness and net grid draw, to prefer renewable energy with storage backing, to study water stress at the basin level and the effect on public supply, to plan for rainwater harvesting and on-site treatment, and to prepare lifecycle plans for electronic waste, batteries and other hazardous waste. Options A, B and D do not match the structure of the document and are therefore wrong. Candidates should memorise the five heads in order, because a question may ask which of a given list is not one of them.
Read the full article: NITI Aayog Unveils Data Centre Evaluation Framework for States
Practice Questions
The Data Centre Evaluation Framework has been released by which body?
- A.Frontier Tech Hub of NITI Aayog
- B.Telecom Regulatory Authority of India
- C.Central Electricity Authority
- D.Bureau of Energy Efficiency
Show answer
The document was drafted with inputs from industry, the Ministry of Electronics and Information Technology, the Ministry of Power and the Department for Promotion of Industry and Internal Trade.
Read the full explanation →India's data-centre capacity has grown from about 375 MW in 2020 to roughly what level now?
- A.Around 800 MW
- B.Around 1.5 GW
- C.Around 5 GW
- D.Around 12 GW
Show answer
From roughly 375 MW in 2020, India's data-centre capacity has multiplied to about this level, carried by rising demand from artificial intelligence, cloud computing, high-performance computing and applications that consume large volumes of data.
Read the full explanation →Who is the Chief Executive Officer of NITI Aayog, present at the release of the framework?
- A.Abhay Karandikar
- B.Debjani Ghosh
- C.Anurag Jain
- D.Arvind Virmani
Show answer
He added that the framework helps States decide in a structured way and speeds up project execution without creating another layer of regulation.
Read the full explanation →What is the full form of VISTAR, the scheme under which the State Dashboard was launched?
- A.Viksit Bharat Initiative for Statistical Transformation, Analytics and Research
- B.Vision for Statistical Transparency, Analysis and Reform
- C.Viksit Bharat Institute for Survey Technology and Reporting
- D.Village Statistics Transformation and Research Initiative
Show answer
VISTAR places emphasis on strengthening subnational statistics and on widening the use of digital tools across statistical processes, dissemination included.
Read the full explanation →How many indicators and themes does the State Dashboard on eSankhyiki currently present?
- A.183 indicators across 8 themes
- B.283 indicators across 10 themes
- C.383 indicators across 12 themes
- D.243 indicators across 15 themes
Show answer
The dashboard presents 283 indicators drawn from 21 statistical products under 10 broad themes, which include agriculture, education, work and wages, and gender and inclusion.
Read the full explanation →